View Issue Details
ID | Project | Category | View Status | Date Submitted | Last Update |
---|---|---|---|---|---|
0000424 | The World of Secfenia | Fields/Workshops | public | 2017-01-20 02:29 | 2018-05-30 19:31 |
Reporter | Logo | Assigned To | daviceroy | ||
Priority | normal | Severity | minor | Reproducibility | have not tried |
Status | resolved | Resolution | fixed | ||
Product Version | 3.0.2a | ||||
Target Version | 3.1.000 | Fixed in Version | 3.1.000 | ||
Summary | 0000424: Pooled hours not used on queued projects | ||||
Description | Hours in the workshop time pool are correctly applied to projects started manually, but not to those starting automatically from a queue | ||||
Steps To Reproduce | 1) Start a workshop project using some, but not all, pooled hours. 2) Queue another workshop project. 3) Wait, up to an hour, for the first project to finish. 4) Observe the number of pooled hours. (Don't know if using artisan skills is necessary to recreate the bug. I didn't try with a single workshop or without multi-tasking.) With 18 hours pooled, I started two 16=hour projects in workshop2. That immediately removed 16 hours from the pool leaving two hours pooled. I then queued four 4-hour projects in workshop1. After an hour, two workshop1 projects had started but the pool count still showed 2 hours remaining and the workshop1 projects showed 4 hours remaining. After another hour and set of workshop events, the 2 hour pool still remained.) | ||||
Tags | Pool Hours Queue Workshop Project Time | ||||
|
This is not a bug, how it is planned to use the hours, only apply to first project. (Reference: http://www.secfenia.org/forums/viewtopic.php?f=4&t=10525&p=152640&hilit=pooled#p152640 ) - Perhaps it could be coded to show that after the first task is started, the pool drops to 0, as it can't be used anymore, to eliminate the confusion? |
|
Re testing note: If it's not a bug, there's a bug somewhere else or an intentional plan to shortchange queued projects. Pooled hours definitely DO apply to subsequent jobs in the current and previous versions. If I MANUALLY start job (which I did later as a work-around) the remaining 2 hours were, in fact, used on 4-hour workshop1 project. It started with 2 hours remaining. Here are the workshop logs showing one of the two 4 hour projects completed in 2 man hours (1 clock hour) Jan 20, 1657 2:55 am You produced in your workshop 4 bacon. Your Steward assisted you in this (-1 Hour Left) You have begun your next project (diamond compound bow) (6042) [+1 Workshop Exp] First Workshop Jan 20, 1657 1:55 am You produced in your workshop 4 bacon. Your Steward assisted you in this (-1 Hour Left) (6040) [+1 Workshop Exp] First Workshop |
|
Thank you for the update. Assigning this to Zach to look into it. |
|
Agreed something odd happening. Will look into this when have a little more free time. Daughter's birthday was today and we been celebrating. |
|
Adding in code to allow queued projects to use pooled hours first taking from multi-tasker pool then regular pool. In addition, Multi-tasker Pool will be shown in new code. Will need to test this. |
|
Added in that the system will show the pooled hours on the main workshop page. |
Date Modified | Username | Field | Change |
---|---|---|---|
2017-01-20 02:29 | Logo | New Issue | |
2017-01-20 02:29 | Logo | Status | new => assigned |
2017-01-20 02:29 | Logo | Assigned To | => testing |
2017-01-20 02:29 | Logo | Tag Attached: Pool Hours Queue Workshop Project Time | |
2017-01-20 20:16 | testing | Assigned To | testing => |
2017-01-20 20:16 | testing | Note Added: 0000215 | |
2017-01-20 20:16 | testing | Assigned To | => daviceroy |
2017-01-21 12:37 | Logo | Note Added: 0000216 | |
2017-01-22 01:34 | testing | Note Added: 0000218 | |
2017-01-27 17:50 | daviceroy | Note Added: 0000230 | |
2018-05-27 15:33 | daviceroy | Sticky Issue | No => Yes |
2018-05-27 15:33 | daviceroy | Sticky Issue | Yes => No |
2018-05-28 15:18 | daviceroy | Note Added: 0000767 | |
2018-05-28 15:18 | daviceroy | Target Version | => 3.1.000 |
2018-05-30 19:30 | daviceroy | Status | assigned => resolved |
2018-05-30 19:30 | daviceroy | Resolution | open => fixed |
2018-05-30 19:30 | daviceroy | Fixed in Version | => 3.1.000 |
2018-05-30 19:31 | daviceroy | Note Added: 0000769 |